News & Media
Phase One of Roof Repair at SXM Terminal Building Completed
SIMPSON BAY, St. Maarten - The Managing Board of the Princess Juliana International Airport – SXM
on Thursday July 5, 2018, announced the completion of Phase One of the roof repair project at the
Terminal Building. The project originally began in March 2018. The completion of this phase is another
step towards the reconstruction of the entire Terminal Building, the Managing Board said.
According to the Projects, Planning and Systems Department of SXM Airport (PPS), the 250 meters long
roof, covering almost 16,000 square meters, was severely damaged in the aftermath of the September
2017 hurricanes. Hurricane Irma had ripped off 70% of the Terminal Building’s roof. Leakage
consequently became a grave concern as it affected the internal operational infrastructure of the airport .
The Ballast Nedam company was contracted to reconstruct the roof in the first phase. The repairs
included waterproofing, steel deck treatment and the installation of the flat metal sheets.
The Managing Board has confirmed that the roof repair plan will be carried out in three phases. Phase 2
of the project has already begun and includes the installation of the roof profiles and panels. Meanwhile,
phase 3 will include the installation of the bullnoses and soffits, which form the perimeter of the roof.
The newly completed roof works (Phase 1) will ensure that the terminal will be watertight. Only after
the installation of the roof profiles, panels, bullnoses and soffits (Phase 2+3 works) will the entire roof be
able to sustain hurricane wind force of 185 miles per hour (Category 5). The overall project is set to be
completed in November 2018.